Project Scope

Con4Mare provided load-out coordination services for Steelwind’s monopile production project. This included load out for interim transport, seafastening, transport, and load in. Our services ensured that these critical operations were conducted safely and in compliance with industry standards. Steelwind Nordenham is producing 64 monopiles for the He Dreiht offshore wind farm, each approximately 70 meters in length, with a diameter of 9.2 meters and a weight of up to 1,300 tons.

Quick Overview

  • Interim transport, Seafastening, Transport, and Load-In

Facts

Con4Mare

Client
Steelwind Nordenham GmbH

Project Phase
Installation & Commissioning

Duration 
2023-2024

Related Projects

See all references
Nordseecluster

Cargo Runs & Onshore Logistics

RWE
German North Sea · RWE
Grid connection systems

Multi-Year Framework for Offshore Infrastructure Services

Siemens Energy
German & UK North Sea · Siemens Energy
DolWin Gamma
He Dreiht offshore wind farm

Marine Coordination

EnBW
German North Sea · EnBW
He Dreiht Marine Coordination
BorWin gamma HVDC converter platform​

Logistic Support Services

Petrofac
German North Sea · Petrofac
Hohe See offshore substation

Offshore Logistics & Marine Operations

Consortium of Engie Fabricom, Iemants and CG
German North Sea · Consortium of Engie Fabricom, Iemants and CG
|
Baltic Eagle offshore wind farm

Marine & QHSE Services

Iberdrola
German North Sea · Iberdrola
Grid connection systems

Maintenance, Repair & Catering

TenneT Offshore GmbH, TenneT TSO B.V.
Dutch & German North Sea · TenneT Offshore GmbH, TenneT TSO B.V.
MEiC TenneT
Offshore wind industry

Cargo Run Service

Various
German & Dutch North Sea · Various
Cargo Run Service
DolWin 6 grid connection

Offshore Logistics

Siemens Energy
German North Sea · Siemens Energy
Spirit of Emden|DolWin6|Spirit of Emden|DolWin6
HVDC converter platforms

Platform Supply Logistics / Vessels

TenneT
German North Sea · TenneT
Spirit of Emden - PSV