Con4Mare provided load-out coordination services for Steelwind’s monopile production project. This included load out for interim transport, seafastening, transport, and load in. Our services ensured that these critical operations were conducted safely and in compliance with industry standards. Steelwind Nordenham is producing 64 monopiles for the He Dreiht offshore wind farm, each approximately 70 meters in length, with a diameter of 9.2 meters and a weight of up to 1,300 tons.
He Dreith offshore wind farm
MP load-out coordination

Project Scope
Quick Overview
- •Interim transport, Seafastening, Transport, and Load-In
Facts
Con4Mare
Client
Steelwind Nordenham GmbH
Project Phase
Installation & Commissioning
Duration
2023-2024